Hope Valley Chlorine PlantCivil works, demolition and detailed concrete works for the new building extensionApr 2018 - current
Barossa Capacity UpgradeCivil works, piling and detailed concrete worksApr 2018 - current
Hope Valley Overflow TroughCivil works, piling and detailed concrete worksFeb - Apr 2018
Wyndham Power Station FacilityPiling, Civil and concrete works for power stationJan – Feb 2018
Uleybury NAWMAPiling, Civil and concrete works for power stationJan 2018
RAAF Tank Interim FacilitiesCivil works and concrete works for squadron headquarters buildings foundation; new car park and concrete pathsApril 2017
Waterproofing the East Stage 2Civil Works, Concrete Works, Installation of Below Ground Pipework and Equipment Install & Reinstatement.April 2016
Hope Valley EL 170 Tank Upgrade EnablingCivil WorksApril 2016
Whyalla WRPDetailed Concrete Works for Water Reclamation PlantApr -July 2016
Concrete Structure and Civil works at OsborneSilo Footings, Hopper receiver structure, Weighbridge, Concrete pavements,Earthworks to hardstand.Feb-Nov 2016
Murray Bridge WWTPCivil Works, Chamber maintenance, Construction of an overflow weirMar-Apr 2016
Skye Coach Road PipelineInstallation of Drive Pipelines and Reinforce concrete pipesMar-Apr 2016
Adelaide Parkland UpgradeDetailed concrete worksOct-Dec 2015
Adelaide Airport Tow Off Area UpgradeConcrete Pavements and FormworkNov-15
Lobethal Quarry Upgrade ProjectDetailed concrete footings including formwork and reinforcing;EarthworksApr - Aug 2015
Prominent Hill UpgradeConcrete works Including Reinforcing and FormworkJan - May 2015
Cultana Range Infrastructure UpgradeCivil works, Intersection upgrade & Tank Crossing Setout, Standard Grenade RangeDec 2014 - Sep 2015
Southern Expressway DuplicationPavings,Erosion Control Works including of reno mattesses/gabion baskets at different locations along the Southern Expressway.Jan - Nov 2014
Adelaide Airport Terminal 1 ExpansionJet Blast Wall,Light Pole Footings,Concrete Paving for Apron WorksApr 2014 - Sep 2015
MacDonald's-West LakesConstruction of a new entranceway to McDonald West LakesDec 2013 - Feb 2014
Aerospace Facility-WingfieldConcrete structures to support jet aircraft manufacturing steel structures.Steel structures were manufactured overseas thus strict tolerances had to be complied withJul - Sep 2013
Metro WTP Underground Fuel Tank ReplacementConcrete Slabs at Hope Valley WTP,Little Para WTP and Barossa WTPApr - May 2013
Anstey HillCivil works,Trenching for Conduit Installation and Pits,Preparation of Slab and Connections to SewerMay - Jun 2013
Adelaide Airport-Stormwater SchemeEarthworks,Reinforcement,Concreting,Pipe and Conduit Installation and Road ConstructionNov 2012 - Oct 2013
Prominent Hill Workshop ExtensionEarthworks and Structural Concreting Including Reinforcing and FormworkJul -Dec 2012
McLaren Vale OverpassConcrete worksApr - Oct 2012
Iron Baron-Whyalla,MineCivil works including Formworks,Reinforcing and ConcretingJan - Nov 2011